Standard Test Device
Name: SH-GY10 High voltage measurement simulation device
Details Introduction
SH-GY10 consists of high-voltage meter cabinet, simulation power cabinet, calculator, control software, modeled on the substation's meter centralized metering mode can be completed training projects include: installing the meter and connecting the power, high-voltage metering simulation, energy meter on-site calibration, reading the meter, rotating the meter.
High voltage meter cabinet
1、Size 800*1000*2260mm, the same as the high-voltage room measurement cabinet.
2, each cabinet can be connected to 1-2 fast meter, simulation of 10kv three-phase three-wire metering mode
3, the internal voltage transformer adopts the simulation of 1:1 transformer, nameplate and appearance according to 10kv/100v design
4, the internal current transformer using simulation 1: 1 transformer, nameplate and appearance in accordance with the 30A/5A design
Simulation power supply cabinet
1、Output voltage:
Output range: 3*57.7/100v
Adjustment range: 0-120% continuously adjustable
Each phase voltage amplitude can be set separately
Voltage symmetry can be set arbitrarily
2、Output current:
Current range: 5A
Adjustment range: 0-120% continuously adjustable
Amplitude of each phase current can be set separately
Each phase current phase can be set separately
3、Phase adjustment: 0.00°-359.99°.
4、Frequency adjustment: 45Hz-65Hz
Column classification